After a long stop in winter time, third 400 kv transmission line project construction in Armenia started again.
At the time being, 6 working teams with about 250 persons are active in the line route, working on earth works, access roads, foundations, tower erection and so on.

Africa is our new target market so we really consider all opportunities there.
Recently HOTCO participated in a tender in Cameroon with MBN Company which was about 220 kv and 90 kv transmission lines there.
Technical and Financial proposal sent to the client on time and we are waiting for result.

As Blue & P group is one of the best teams in Iran and its region, HOTCO management decided to start cooperation with them to expand its activities and increase its market share in power sector in Iran and overseas.
We are negotiating about our cooperation and strategic partnership with Blue & P group.